Author Topic: QE2 1994 Refit: Project Lifestyle  (Read 4159 times)

0 Members and 5 Guests are viewing this topic.

Online Lynda Bradford

Re: QE2 1994 Refit: Project Lifestyle
« Reply #15 on: Jul 24, 2020, 04:50 PM »
New Suite of Orientation Signage

Naming of individual public rooms were agreed with Cunard and a graphic style for a new style of lettering was designed by McNeece, who also devised the overall orientation scheme, designed each individual sign, and positioned them through all public spaces, interior as well as exterior, and in cabin accommodation alleyways and entrances.

UK-based Signs 2000 was commissioned to produce a total of 446 signs (in fire-rated composite backboard) in two groups – directional signs in five sizes and information signs, also in five sizes. Sign 2000 put all the materials used through vigorous tests to make sure they were light in weight and capable of being easily changed. Dual-lock fastenings were provided to provide security from souvenir hunters while giving a removable facility.

Minor modifications were made to the safety directional signage as there were only minor changes to escape routes from the lower spaces and the main assembly points remained as before.

Lighting

In November 1993 Alex McCuaig had asked Adam Grater and Peter Phillipson of DHA Design Services to carry out a survey of the lighting. A review of the public rooms was done to form a strategy of how lighting in public areas would be designed.  Ship’s engineers had input to the strategy so as to identify problems they had experienced with lighting equipment they had inherited. 

The report was accepted by Cunard, and incorporated into the overall ‘Project Lifestyle’ masterplan. DHA were appointed as the lighting designers for the refit.

The lighting of the public spaces on board was seen as a major element in creating the right atmosphere at various times of both day and night. In order to vary the mood and pace around the ship and establish boundaries around spaces, most of the new lighting was dimmable tungsten.

One example of this strategy was the promenade which ran along the outer walls of the Queens Room. Here, dimmed lighting was used to ‘screen’ people walking by so they didn’t distract others in the central space. Another was the way that public areas were gradually toned down at night, starting with bars and lounges at the forward end of the ship. This encouraged passengers to move down to the Yacht Club and Lido which were designed to be the liveliest, most concentrated late night / early morning spaces.

Much of the ship’s original equipment had been made by Philips Lighting back in 1968 and was still functioning. It needed upgrading only because it was at the end of its life. In all, 2,252 new light fixtures were fitted throughout QE2. The new lighting designs were undertaken between May and early July 1994.

Originally, nearly all the public rooms were to have new ceilings, allowing the designers to put lighting where they wished, but subsequent restraints in the entire refit budget led to restrictions in original intentions. This posed a further problem – to replace old lighting with similar luminaires, on a one-for-one basis, would hardly have been appropriate as the new interiors did not suit the existing holes in the ceiling. Fire authorities would not have allowed the filling of holes with plaster so DHA had to design a series of retro fit luminaires that could be set rigidly to aim the light in one direction during the commissioning.

Miscellaneous

Thousands of pieces of furniture and other items had to be purchased for the refit work. These included:

- 300 tons of steel, aluminium, ceramics and wood
 - 2,252 new light fixtures
- 74,200 square yards (62,000 square metres) of fabric for chairs and curtains
- 40,000 square yards (38,000 square metres) of new carpet in 25 separate carpet designs
- 12 pieces of commissioned artwork
- 8,000 gallons (12,000 litres) of fresh paint
- 10,000 pints of lager stocked in the new Golden Lion Pub
- 600 new books to add to the 6,000 already in the largest Library at sea
- 500 additional place settings for the new restaurant areas
- 2,000 new bedspreads
- 24 exhibits displaying nautical memorabilia would form part of the new Heritage Trail
- 3,000 new uniforms for the 1,000 crew
- 308 colours added to her design scheme

The Heritage Trail

See Heritage topics
see the Heritage Trail forum topics for more details

A key element of the new design scheme was the introduction of The Cunard Heritage Trail on board. The Heritage Trail was designed to reflect the history and heritage of the Cunard Line and its ships in an historical exhibition of nautical memorabilia.

In strategic locations throughout the ship, exhibits including original charts, ship models, flags, pennants, paintings and, among many other items, ship models were placed in specially-designed showcases made of burr oak vaneer.
I was proud to be involved with planning QE2's 50 year conference in September 2017 in Clydebank

Online Lynda Bradford

Re: QE2 1994 Refit: Project Lifestyle
« Reply #16 on: Aug 02, 2020, 10:37 AM »
We can only provide this information thanks to the research work of Michael Gallagher.  Please do not copy without his permission

Promenades and Stairways

Simplifying the layout of the ship was one of the key elements of ‘Project Lifestyle’ in order to revitalise the original peripheral circulation plan in the public areas.  In all, one million square feet of corridor space was worked on.

Changes to Promenades and Stairways spaces aimed to:

Increase the visibility of various activities and spending opportunities
Improve orientation (aided by the heritage trail) to improve flow and minimise maintenance
Address and improve decor, which was confusing, garish and hard to maintain
Improve stairway artwork displays, including themed posters on stairs. 

Quarter Deck plan had remained fairly well intact over the years while the Upper Deck had become more fragmented

The promenade routes on both decks were substantially improved with the addition of connecting elements turning them in completely surrounding loops.

On the Quarter Deck, the existing forward connection at D Stair was complemented with a new beamwise passage aft of the G Stair, adjacent to the new Lido Restaurant.

A passage similar to that was added aft on Upper Deck at the entrance to the new Yacht Club while the new Crystal Bar on that deck forward provided a new beamwise promenade.

Boat, Upper and Quarter Deck Promenades

The new design for the promenades and the stairways was conceived together. The promenades received new caramel carpets with green and mulberry inset unique to each deck. The bulkheads received specialist paint finishes, warm umber curtains and blinds with European oak handrails.

The finishes of all promenade areas were unified to reinforce the promenade experience – materials and stylings were restrained to present a truly elegant liner character. Coloration from adjacent rooms drifted into the relevant promenades and punctuated the journey along the ship.

Staircases

All staircases received extensive work and the existing 1969 style was changed for the first time. Generally, all carpets were replaced with ones of new designs specifically for this project, and mainly woven by Brintons. The majority of the ceilings were of metallic panelling supplied by Dampa.

Main Staircases D, E and G
Design objective: rich and refreshing look

New carpets (in rich mulberry with inlaid motifs in Sherwood green to the stairway landings) and balustrade panels were redone in a specialist paint finish incorporating various shades of green with gold highlights.

See also the following topics that may be of interest:

D Stairway topic
E Stairway topic
G Stairway topic

Staircases A, B, C, F and H
Design objective: clean and crisp look

New carpets (in rich mulberry with inlaid motifs in Sherwood green to the stairway landings) and all bulkheads were finished in specialist wall coverings with reflective shades of warm gray, silvers and gold. The balustrade panelling was repainted in a plum with copper highlights. The balustrade handrail was painted in a darker plum while deckheads were finished in off-white. Lift doors were redone in plum. 

See also topics that may be of interests:

A Stairway topic
B Stairway topic
C Stairway topic
H Stairway topic
QE2 Stairways and Lifts

Lifts - All the external lift doors were re-covered in the same colour as the handrails in that particular staircase and the inside of the doors were redone in silver with the Cunard lion placed in the centre of each door.

« Last Edit: Aug 02, 2020, 06:16 PM by Lynda Bradford »
I was proud to be involved with planning QE2's 50 year conference in September 2017 in Clydebank

Online Lynda Bradford

Re: QE2 1994 Refit: Project Lifestyle
« Reply #17 on: Aug 03, 2020, 09:57 AM »
We can only provide this information thanks to the research work of Michael Gallagher, please do not use without his permission.

Passenger Accommodation

McNeece had the responsibility for updating all passenger cabins, with restrictions applied that structural modification were to be confined to cabin toilets. 

- The cabin refurbishment programme accounted for 30% of the total interior redesign cost
- The cabins represented more than 50% of the area encompassed by the refit
- Prior to the refit date contractors had sealed off blocks of cabins to check for fibre before preparing rooms for the refurbishment and structural alterations
- The new designs set minimum standards of cleanliness, comfort and functionality appropriate to each grade

Penthouse Suite: All Penthouses were luxuriously refurbished with all-new furnishings in a rich style.

Cabin refurbishment: All cabins received new soft furnishings: bedspreads, carpets, curtains, upholstery etc. New chairs and or stools were installed and all settees were re-covered. The new designs were in keeping with both the traditional concepts with modern materials that were designed to increase passenger convenience and comfort and offer a new feeling of warmth.

In all, 2,000 new bedspreads were supplied.

New Bathrooms

Urgent priority was given to replacing the original 1960’s style bathrooms with modern ergonomically designed fittings and easy to clean surfaces, which would conform to hotel standards.  The refurbishment of 1000 bathrooms would be at a cost of £4.8 million of the £32 million hotel budget.

To complete the refurbishment of 1000 bathrooms, a rolling programme of work was planned from when QE2 returned from her 1994 World Cruise in April until November. However the start date was extended to June with work not eventually starting until July, as a result of Cunard management not making a decision on the schedule.  Southampton firm Tramline was contracted to do the work. 

It was accepted that improvements to basic functions, such as the primary plumbing system would prove too expensive so every effort was made to make the bathrooms as efficient as possible.

The bathrooms would be refurbished to three different standards:

Ultra Deluxe Cabins: 220 cabins in this category (the 1987 Penthouses 8011 – 8018 were excluded). The new design consisted of Crema Marfil beige marble floor and bulkheads, Burnt Sienna marble vanitory units and Bird’s Eye maple trim.

Deluxe Cabins: 300 cabins in this category – approximately 209 with baths and 91 with shower enclosures. The new design consisted of tan and white tiles, copper tones granite vanitory unit and Bird’s Eye maple trim.

Premium Cabins: 464 cabins in this category – located mainly on Four and Five Decks. The new design consisted of beige laminate bulkheads, white ceiling and tiles, copper toned granite vanity unit and Bird’s Eye maple trim.

Within each category a small number would be adapted to the needs of disabled passengers.

The cabins would receive a brand-new bathroom (new tiles, vanity units, showers / baths, sinks and toilets) while all toilet compartments were to be rebuilt to a recognisable standard throughout the various grades of accommodation.

Smaller cabin bathrooms would have timber laminate tops to the units fitted, while the premium grades would receive granite and the higher grades receiving marble tops - but with individual units being of similar dimensions.

New elements included free-standing cone-shaped washbasins mounted on burred veneer black panels, polished granite sink tops and the vertical, diffused fluorescent battens down both sides of the mirror units.

All shower units were to be replaced. The fibreglass showers, originating from QE2’s construction, had reached the point of detracting from the acceptability of her accommodations by modern standards.

Shower installation work while QE2 was in service:

Some 509 new showers were installed while QE2 was still in service between July and November 1994. This was accomplished by way of custom knock-down shower units designed specially for QE2 by McNeece and made by British manufacturer Blondecell Limited. These were manufactured so that they could be erected ‘in-situ’ aboard the ship, in minimum time, without dismantling the accommodation alleyways.

The works to bathrooms started in July 1994 with up to 120 skilled men being involved. This rolling programme would continue until 19 November and the dry-dock period commencing. Blocks of cabins would be taken out of service sequentially until the work was finished – with noisy work and fumes being kept to an absolute minimum.

The workers completed preparations in sixty units in each ten-day period, and over 300 items (many from other suppliers who in turn had to be sub-contracted) required for each cabin’s update were stored in a dockside shed in Southampton in readiness for transference to the ship during her short turnarounds.

Naturally such a massive undertaking would not be without its problems and as Summer 1994 progressed more and more problems were encountered with the bathroom project. Last minute offloads became a common occurrence and the disruption to passengers on board resulted in more and more complaints about the work. Asbestos removal was also more problematic. By August the revenue loss due to the revised cabin requirements was over $1.9 million.

The work really began in earnest after QE2’s arrival at the shipyard on 20 November but the project was far from finished upon her return to service on 17 December. Trimline staff had to remain with the vessel for weeks after the project had originally been scheduled to finish in order to complete the work.

In the end 151 cabins would not receive any bathroom work at all.

Later John McNeece would claim that the bathroom problems experienced where due to Cunard’s senior management authorising QE2’s own officers and crew to replace steelwork and plumbing in the cabin areas (there was serious corrosion of steel plating below bathroom floors due to long-term water damage) without informing McNeece. So, this aspect of the project, plus a new ring mains in the corridors, was not accounted for in McNeece’s planning strategy - and it was his 14-strong fit-out snagging team that had constantly to re-inspect areas that had already been deemed complete. He recalled that:

Quote
“There were huge pressures on Cunard’s already stretched project managers who appeared to lose control. No sooner had blocks of cabins and corridors been carefully refurbished than QE2’s own crewmembers began to dismantle them again to replace the plumbing and electrics - and this caused damage to the new ceilings, wall finishes, furniture, fittings and carpets and delays to the overall project. Later, one week before the work was due to be completed, the Enchanted Isle charter expired and so the subcontractors were transferred to hotels and guesthouses in Hamburg. Of course, they hit the town and this brought a decrease in productivity during the closing stages, including some instances of sabotage, presumably in the hope that their contracts might be extended to make good the damage”.

Accommodation for disabled people: Four staterooms were redesigned, using the latest technology. The rooms involved were:

Q3 Grade - 1048 and 1051
Q4 Grade - 1062 and 1064

In these, the pneumatically operated hinging outer doors and sliding bathroom doors could be controlled from a special transmitter carried by the passenger, both on approach to the cabin and to assist callers to enter. This transmitter could also be used to control lighting, curtains and television.

Part of the McNeece brief, on the disabled cabin design was to ensure that the cabins were not so obviously for disabled people as to deter other passengers using them as normal.

New Cabin Grading

The existing 24 cabin grades were replaced by 18 grades grouped into four levels of luxury and more closely linked to the restaurants on board. All cabins were reviewed for size, amenities and location and then re-graded, reducing the categories from 18 doubles to 13 doubles.

   Q Grills Class      Queens Grill               
   P Grills Class      Princess or Britannia Grills         
   C Deluxe Class      Caronia Restaurant            
   M Premium Class   Mauretania Restaurant         

This regrading also saw an end to the formal two-class operation of QE2 when on the Atlantic.
I was proud to be involved with planning QE2's 50 year conference in September 2017 in Clydebank

Online Lynda Bradford

Re: QE2 1994 Refit: Project Lifestyle
« Reply #18 on: Aug 04, 2020, 09:42 AM »
Technical Work

Extensive technical overhaul work was undertaken on the hull and machinery spaces of QE2 at a cost of around £13 million.

The existing automatic sprinkler system in the public areas and service spaces was modified and extended to comprise 8,700 heads controlled by 68 sets of section valves.

Additional fire doors and control systems were fitted and new fan rooms for additional air conditioning units were supplied and fitted.

For the ship's waste disposal system a new garbage grinder plant was supplied.

The heaviest work undertaken arose from the scheduled inspection of the propellers. The starboard tailshaft was the subject of a full survey, necessitating its wholesale removal while the portside tailshaft was partially withdrawn. The stern tube bearings were scrutinised on the starboard side, while the propellers shaft seals and propeller hub seals were renewed in each installation, the propeller blades were re-conditioned where necessary.

The controllable-pitch propeller oil was replenished.

The boilers were cleaned, removing soot deposits.

Seven additional pumps were supplied by Hamworthy from its Dolphin range for the air-conditioning and saltwater circulation and salt water general service systems.

Four oil pre-heaters were installed.

The bow thrusters and stabilisers were overhauled.

2,500 square metres of bottom plating was hydroblasted.

The air-conditioning system was overhauled.

A new integrated bridge system was installed by Kelvin Hughes featuring new radar displays, transceivers, workstations and electronic chart displays.
I was proud to be involved with planning QE2's 50 year conference in September 2017 in Clydebank

Online Lynda Bradford

Re: QE2 1994 Refit: Project Lifestyle
« Reply #19 on: Aug 04, 2020, 09:52 AM »
Exterior

Aft Profile:

The removal of the Magrodome and the Alpha and Beta tenders improved the exterior profile of the ship and reclaimed more open deck space.  This removal of the Magrodome resulted in an additional 5,000 square feet of deck space being created aft of the new Yacht Club. Additional windows (for the Yacht Club) were cut into the superstructure aft on Upper Deck. The staircase arrangement was also altered with new stairs built (port and starboard) from Boat Deck down to Upper Deck and the existing stairs (port and starboard) from Upper Deck down to Quarter Deck were altered.

Livery:

MET Studio was responsible for the new livery and their concept centred on the reinforcement of the ship's original sleek and elegant horizontal lines. QE2 thus exchanged her trademark black, red and white for Cunard's new corporate colours of blue, red, white and gold.

‘Speedstripe’

The white superstructure was given a stripe of the new Cunard tricolor - red, gold and blue - running along the lower section of the structure, stretching for 200 metres along each flank (with a width of 500 mm). The stripe was a key component of the new livery and took the unusual form of a decal, applied with fierce adhesive, more normally used for aircraft and road vehicles. It was designed to give the same effect as paintwork but made it much easier to maintain and keep its perfect, clean lines over time in a way that retouched paintwork could not. It took six days to apply this, the longest ‘speed-stripe’ in the world.

Cunard Name: The Cunard name in Cunard red was moved further forward underneath the bridge on each side and, above the name, the golden Cunard symbol - a lion rampant - was placed, standing four metres high.

Hull: The QE2's hull was painted royal blue with a thin gold stripe before the red boot-topping which continued right across the underside of the ship.

Topic: Speedstripe and Cunard Lion Logo

Lifeboats

Alpha and Beta: The two large tenders, Alpha and Beta, located alongside the Magrodome facility, were removed as were their complicated supports. These had disrupted the flow of the open decks aft so their removal gave QE2 a much cleaner open deck profile. Alpha and Beta were sold to a new owner in Croatia.

Alpha Beta Tenders topic

New Tenders:  The removal of Alpha and Beta, and the need to renew two of the existing tenders, necessitated in the installation of two new 112-seat Harding catamaran-type launches which were installed on new davits on the Boat deck, midships, numbers 13 and 14. These 12-knot vessels were innovative in design and particularly suitable for the easy boarding of passengers. As partially enclosed lifeboats, each tender could accommodate 150 passengers. Propulsion was by twin 290 bhp diesel engines driving 600-mm diameter alloy bronze propellers.

One Deck Aft: One deck extended to right aft in order to accommodate 12 liferafts. The two small cranes originally located on Two Deck aft were relocated up to One Deck.

The flag pole now railed off and now access for passengers to extreme aft of vessel.

Top of the Ship: Three radar domes were added on the top of the ship. The five-foot satellite aerial atop of the mast was removed.
I was proud to be involved with planning QE2's 50 year conference in September 2017 in Clydebank

Online Lynda Bradford

Re: QE2 1994 Refit: Project Lifestyle
« Reply #20 on: Aug 04, 2020, 09:58 AM »
Gross Tonnage: As a result of the changes, particularly the extensive deck alterations and extensions, the 69,052-ton Queen Elizabeth 2 was re-measured upon returning to service and was re-listed as being 70,327-tons.


Return to Service: When Queen Elizabeth 2 returned to service on 17 December 1994 media outlets reported on the uncompleted work on the ship and the fact that workmen had to travel with the ship to New York to complete the work.  However the majority of the project was achieve, the 1995 World Cruise was not postponed and the result of this refit was that QE2 was transformed into a ship with a new, fresh image, ready for the next 25 years. . Although she was commissioned in 1969, QE2 was effectively less than eight years old in an engineering sense (having been re-engined in 1987) and ‘new’ in the context of her interiors.

End of Project Lifestyle information
I was proud to be involved with planning QE2's 50 year conference in September 2017 in Clydebank

Online Thomas Hypher

  • Queens Grill Diner
  • *****
  • Posts: 2879
  • Total likes: 5604
  • QE2 started a dream to go to sea - now a reality!
Re: QE2 1994 Refit: Project Lifestyle
« Reply #21 on: Aug 04, 2020, 04:46 PM »
Excellent information on this refit, an important point in the ship's history, also giving us the QE2 many of us knew and loved, and most of the QE2 in Dubai today despite Dubai's marketing to the contrary. Thank you Lynda and Michael!
First sailed on QE2 in August 2003 aged 6 years old. Last sailed on QE2 in July 2008. Last saw the seagoing QE2 in person from the decks of QM2, on QE2's last Transatlantic crossing (Eastbound tandem) in October 2008. Visited QE2 in her new life, in Dubai, in January 2020 and August 2022.

Online Isabelle Prondzynski

Re: QE2 1994 Refit: Project Lifestyle
« Reply #22 on: Aug 04, 2020, 08:54 PM »
Lynda, congratulations are long overdue! Thank you so much for all this fabulous documentation, which you are contributing to the Forum, with your committed work, making it a precious source for future researchers. Big thanks are also due to Michael, who is providing so much of the essential material.

Offline June Ingram

  • Global Moderator
  • Queens Grill Diner
  • *****
  • Posts: 9582
  • Total likes: 6516
  • Beautiful, elegant QE2 - forever Queen of the Seas
Re: QE2 1994 Refit: Project Lifestyle
« Reply #23 on: Aug 05, 2020, 01:32 AM »
Many thanks, Lynda, for this enormous project, containing so much valuable information organized in an orderly way ! It is a valuable contribution to the archives of The QE2 Story and represents many hours of work on your part ! Thank you, Michael, for making information available to Lynda !
QE2 - the ship for all of time, a ship of timeless beauty !

Offline Chris

Re: QE2 1994 Refit: Project Lifestyle
« Reply #24 on: Aug 05, 2020, 04:09 AM »
Here she is in February 1995 fresh out of the Project Lifestyle refit. This was when I first “met” QE2. She was magnificent in the original Project Lifestyle configuration.


🎥 Check out my QE2 & Cruise Ship Videos: https://www.youtube.com/chrisframeofficial/

Offline Chris

QE2 in 1996
« Reply #25 on: Aug 05, 2020, 04:12 AM »
Thought you’d enjoy a little walking tour of QE2 from 1996. She is still featuring her original Project Lifestyle refit interior here before all the alterations to carpets and public rooms done in the post-Carnival days.


🎥 Check out my QE2 & Cruise Ship Videos: https://www.youtube.com/chrisframeofficial/

Online Rob Lightbody

  • Administrator
  • Queens Grill Diner
  • *****
  • Posts: 12352
  • Total likes: 15895
  • Helping to Keep The Legend Alive
    • Rob Lightbody dot com
Re: QE2 1994 Refit: Project Lifestyle
« Reply #26 on: Aug 05, 2020, 06:25 PM »
Lynda & Michael - your sustained efforts on this topic are outstanding and I've enjoyed revelling in all the detail.

It seems to me to have been an outstanding refit.  So many things they did seemed to make perfect sense, and to make the ship better, less confusing and more coherent.  Many things I enjoyed when I returned on board in 2008 and 2008 were from Project Lifestyle.

I have some questions for those regular QE2 travellers from this time - Myles and John maybe?

When you first went aboard after Project Lifestyle (once things had settled down - not caring about the post refit problems) - what did you think?  Were you impressed with the new layout and designs etc?  What did you like and what did you not like?

Also - later - did any initial irritations you had go away?
Passionate about QE2's service life for 40 years and creator of this website.  I have worked in IT for 28 years and created my personal QE2 website in 1994.

Online Isabelle Prondzynski

Re: QE2 1994 Refit: Project Lifestyle
« Reply #27 on: Aug 05, 2020, 08:50 PM »
Here she is in February 1995 fresh out of the Project Lifestyle refit. This was when I first “met” QE2. She was magnificent in the original Project Lifestyle configuration.

Nice compilation, Chris, and I liked the background music (which I know very well, but I cannot put my finger on the name right now...). Good to see all your first impressions of the ship.

Online Thomas Hypher

  • Queens Grill Diner
  • *****
  • Posts: 2879
  • Total likes: 5604
  • QE2 started a dream to go to sea - now a reality!
Re: QE2 1994 Refit: Project Lifestyle
« Reply #28 on: Aug 05, 2020, 09:12 PM »
Nice compilation, Chris, and I liked the background music (which I know very well, but I cannot put my finger on the name right now...). Good to see all your first impressions of the ship.

Waltz Of The Flowers From The Nutcracker by Tchaikovsky. I recognised it too but thought it was from his Swan Lake instead.
First sailed on QE2 in August 2003 aged 6 years old. Last sailed on QE2 in July 2008. Last saw the seagoing QE2 in person from the decks of QM2, on QE2's last Transatlantic crossing (Eastbound tandem) in October 2008. Visited QE2 in her new life, in Dubai, in January 2020 and August 2022.

Online Isabelle Prondzynski

Re: QE2 1994 Refit: Project Lifestyle
« Reply #29 on: Aug 05, 2020, 09:25 PM »
Waltz Of The Flowers From The Nutcracker by Tchaikovsky. I recognised it too but thought it was from his Swan Lake instead.

Thank you very much, Thomas! I had a feeling it was one of the Tchaikovsky ballets, but I had no easy way of checking.