Author Topic: QE2 Refit and Repair 3 to 21 December 1974  (Read 2420 times)

0 Members and 1 Guest are viewing this topic.

Online Lynda Bradford

QE2 Refit and Repair 3 to 21 December 1974
« on: Apr 07, 2016, 07:46 PM »
The QE2 Story would like to thank Michael Gallagher for giving his permission to extract information from information he had compiled on refits and allowing us to make this information available on the QE2 Story Forum.

Timescale: Three weeks
Date: 3 – 21 December 1974
Contractor/Place: Schiedam, Rotterdam and Southampton
Total Cost: £647,000
Captain: M Heir

Background:

On 23 August 1974 Cunard confirmed that QE2 would be refitted in Rotterdam during her annual overhaul in 1974 – the first time the vessel would go to a non-UK yard for refitting.

A Cunard statement:

“The work of QE2’s annual overhaul was offered to Vosper Thornycroft Ltd at Southampton, but the company were unable to take it on because of prior work. The ship was then offered to Scott Lithgow on the Clyde, but they were also unable to undertake the work”.

In addition to usual range of overhaul work, this refit would focus on preparing the ship for her Maiden World Cruise in 1975 and it was this added focus (plus the problems with ‘added work’ during the 1972 refit) which persuaded Vosper Thornycroft, who had other ships to handle at the same time, to refuse to accept QE2. The seven-day schedule was also a factor. Vosper Thornycroft emphasised that their reputation would suffer if they took on too much work, then upset owners by not completing jobs on time.

Despite these facts there was still a furore of protest from the media, unions and official bodies.

An amount of £407,000 was allowed for normal overhaul work, covering both technical and furnishing repairs; some £150,000 was spent of insurance work and £90,000 was spent on capital items.

QE2 entered Dry-Dock on 4 December 1974 and left on 19 December, 1974.
 
While at the yard, permanent repairs were made to the two 1974 emergencies:

Permanent repairs were undertaken in the engine room after temporary repairs had been made following QE2’s breakdown off Bermuda in April.

Cherbourg Incident:
After QE2 had struck the quay in Cherbourg on 27 October temporary repairs to the gash in the ship’s side had been made by the French navy. Now, permanent repairs were undertaken and further shell dents found below the waterline that had been discovered in Rotterdam were repaired and crew and passenger cabins damaged in the collision received attention.

Return to Service:

The crew were flown out to rejoin QE2; on the passage back to Southampton they had the task of making QE2 ready to embark passengers.

The Board Report Minutes dated 6 January 1975 noted:

   “The annual overhaul has been completed in Rotterdam in a most efficient manner. All items submitted for work were completed on time and the final cost agreed before the ship left the yard. The cost was within blueprint. Details of this highly successful overhaul will be contained separately in the Technical Manager’s report”.

« Last Edit: Apr 18, 2016, 09:56 AM by Lynda Bradford »
I was proud to be involved with planning QE2's 50 year conference in September 2017 in Clydebank

Online Lynda Bradford

Re: QE2 Refit and Repair 3 to 21 December 1974
« Reply #1 on: Apr 18, 2016, 10:22 AM »
QE2's annual overhaul was scheduled for December 1974, but as a result of two separate incidents the ship had required other repairs that year in April and October.(8 – 25 April 1974) and October(27-31 October, 1974 Repair)

Because there are discussion on the incidents the refit and repair topic is meant only to give more details of the refit or repair, but not to take away from the first hand knowledge of the incidents that occurred that year. 
I was proud to be involved with planning QE2's 50 year conference in September 2017 in Clydebank

Offline Twynkle

Re: QE2 Refit and Repair 3 to 21 December 1974
« Reply #2 on: Apr 18, 2016, 12:34 PM »
Hi Lynda.
Thank You - there's evidence of much hard work here.
These records are fascinating.

Online Isabelle Prondzynski

Re: QE2 Refit and Repair 3 to 21 December 1974
« Reply #3 on: Apr 26, 2016, 11:06 PM »
Hi Lynda.
Thank You - there's evidence of much hard work here.
These records are fascinating.

Thank you indeed, Lynda. Amazing to see all the information you have assembled in these topics. The QE2Story is becoming a wonderful library of QE2 in so many ways, and you have contributed to this greatly.

Offline June Ingram

  • Global Moderator
  • Queens Grill Diner
  • *****
  • Posts: 9582
  • Total likes: 6516
  • Beautiful, elegant QE2 - forever Queen of the Seas
Re: QE2 Refit and Repair 3 to 21 December 1974
« Reply #4 on: Apr 27, 2016, 02:40 AM »
Hi Lynda - Your work regarding refits and repairs is adding so much information to QE2's history and in such an orderly way.  Thank you so much for doing all of the work involved and thereby adding to the research capabilities of The QE2 Story and Forum !  June  :)
QE2 - the ship for all of time, a ship of timeless beauty !